What Happens After Planning Permission?

Ten practical steps from decision notice to technical design, tender and start on site.

Prepared 20 November 20265 min readBy Hepburn Architects
Quick answer

The essential position

Planning consent establishes an approved proposal, not a fully designed or construction-ready project. Review the conditions, coordinate the technical work and complete the other necessary procedures before the contractor starts.

Need advice on a specific property?Call David directly on 07720 813035 or book a free consultation.

Key points

  • Read the decision notice and conditions before assuming you can commence.
  • Develop technical drawings and consultant designs for the actual building.
  • Tender on coordinated information and record any design changes.

1. Steps 1–3: secure the planning position

1. Read the decision notice, approved drawings and every condition. 2. Record who will prepare each condition submission and when approval is required. 3. Check whether approved plans need a non-material amendment, section 73 application or fresh permission before a change is built.

Permission commonly has an implementation time limit stated in the decision notice. Starting work without satisfying a pre-commencement condition may create serious legal uncertainty; obtain project-specific advice if in doubt.

  • Decision and plan register
  • Conditions matrix
  • Change-control record

2. Steps 4–6: coordinate technical design

4. Confirm the applicable Building Regulations route and current technical standards. 5. Commission structural, drainage, thermal, acoustic and other specialist design as appropriate. 6. Agree construction details, specifications and interfaces among designers.

Planning drawings show the consented shape and use; they do not normally describe the foundation, beam design, insulation, cavity barriers or site-specific workmanship required.

  • Technical package
  • Consultant responsibility schedule
  • Building Control arrangements

3. Steps 7–8: price and programme

7. Issue the same complete information to each builder and require a priced schedule with clear exclusions. 8. Set a realistic construction programme, allowing for long-lead items, surveys, party-wall procedures and service connections.

A low quote with gaps is not the same as the lowest whole-project cost. Ask for written clarification before accepting assumptions or provisional sums.

  • Comparable tenders
  • Programme and site logistics

4. Steps 9–10: authorise the start

9. Check the building contract, insurance, safety arrangements, access and neighbour communications. 10. Hold a start-readiness review and retain confirmation of outstanding approvals and responsibilities.

Keep the approved information accessible throughout construction. If the design changes materially, check the planning and technical implications before it is installed.

  • Contract and insurance
  • Recorded go/no-go meeting
Frequently asked questions

Questions homeowners commonly ask

Can I change the windows after planning approval?

It depends on what was approved and the scale of the change. Check the approved drawings and ask whether an amendment is required.

Does planning approval cover Building Regulations?

No. Planning and Building Regulations are separate systems.